| Assessment Year | 1988 |
|---|---|
| Principal Product | PISTONS, MOTORS, PUMPS |
| NAICS |
n/a
|
| SIC | 3594: Fluid Power Pumps and Motors |
| Sales Range | $10 M to 50M |
| # of Employees | 180 |
| Plant Area |
n/a
|
| Annual Production | 140,000
pieces
|
| Production Hrs. Annual | 4,950
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $208,522 | 2,775,791 |
kWh
|
$0.075 |
| Natural Gas | $41,865 | 12,827 |
MMBtu
|
$3.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,030 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,783 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4312: Improve lubrication practices | $3,862 | - |
$3,862
51,290
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,535 | - |
$1,535
20,516
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $43,747 | $33,748 |
$43,747
582,356
kWh
|
- | - | |
| 04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $885 | $1,000 |
$1,086
14,361
kWh
|
$(-201.0)
-
MMBtu
|
- | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,732 | - |
$3,732
-
kWh
|
- | - | |
| 06 | 2.3132: Recharge batteries on during off-peak demand periods | $1,189 | - |
$1,189
-
kWh
|
- | - | |
| 07 | 2.2437: Recover waste heat from equipment | $2,695 | $1,500 | - |
$2,695
-
MMBtu
|
- | |
| 08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $385 | $500 | - |
$685
-
MMBtu
|
$(-300.0) | |
| TOTAL RECOMMENDED | $58,030 | $36,748 |
$55,151
668,523
kWh
|
$3,179
-
MMBtu
|
$(-300.0) | ||
| TOTAL IMPLEMENTED | $53,783 | $36,248 |
$51,289
617,233
kWh
|
$2,494
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs