ITAC Assessment: WI0028
ITAC logo
ITAC Assessment: WI0028
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product SHEET METAL ASSEMBLIES
NAICS
n/a
SIC 3524: Lawn and Garden Tractors and Home Lawn and Garden Equipment
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 7,200
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $222,626 4,379,543
kWh
Natural Gas $93,794 27,326
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,709 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,649

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $11,017 - $11,017
216,589
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,745 - $2,745
53,927
kWh
- -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,249 - $1,249
20,223
kWh
- -
04 2.2437: Recover waste heat from equipment $5,774 $1,200 - $5,774
-
MMBtu
-
05 2.6121: Reduce hot water temperature to the minimum required $319 - $279
5,569
kWh
$40
-
MMBtu
-
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,060 - $2,030
-
kWh
- $(-970.0)
07 2.7226: Use computer programs to optimize hvac performance $1,545 $5,000 $1,545
30,481
kWh
- -
TOTAL RECOMMENDED $23,709 $6,200 $18,865
326,789
kWh
$5,814
-
MMBtu
$(-970.0)
TOTAL IMPLEMENTED $22,649 $6,200 $16,835
326,789
kWh
$5,814
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs