| Assessment Year | 1988 |
|---|---|
| Principal Product | SHEET METAL ASSEMBLIES |
| NAICS |
n/a
|
| SIC | 3524: Lawn and Garden Tractors and Home Lawn and Garden Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $222,626 | 4,379,543 |
kWh
|
$0.051 |
| Natural Gas | $93,794 | 27,326 |
MMBtu
|
$3.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,649 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4312: Improve lubrication practices | $11,017 | - |
$11,017
216,589
kWh
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,745 | - |
$2,745
53,927
kWh
|
- | - | |
| 03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,249 | - |
$1,249
20,223
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $5,774 | $1,200 | - |
$5,774
-
MMBtu
|
- | |
| 05 | 2.6121: Reduce hot water temperature to the minimum required | $319 | - |
$279
5,569
kWh
|
$40
-
MMBtu
|
- | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,060 | - |
$2,030
-
kWh
|
- | $(-970.0) | |
| 07 | 2.7226: Use computer programs to optimize hvac performance | $1,545 | $5,000 |
$1,545
30,481
kWh
|
- | - | |
| TOTAL RECOMMENDED | $23,709 | $6,200 |
$18,865
326,789
kWh
|
$5,814
-
MMBtu
|
$(-970.0) | ||
| TOTAL IMPLEMENTED | $22,649 | $6,200 |
$16,835
326,789
kWh
|
$5,814
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs