ITAC Assessment: LE0103
ITAC logo
ITAC Assessment: LE0103
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Nonferrous castings
NAICS
n/a
SIC 3369: Nonferrous Foundries, Except Aluminum and Copper
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 50,000
ft2
Annual Production 1,000,000
lb
Production Hrs. Annual 2,250
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,165 1,991,440
kWh
Electricity Demand $1,416 1,416
kW-mo/yr
Natural Gas $39,954 5,963
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,747 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,158

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
01 2.2443: Re-use or recycle hot or cold process exhaust air $14,809 $49,595 $14,809
185,114
kWh
- - -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $16,104 - - $16,104
-
kW-mo/yr
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,154 $1,600 $1,314
16,420
kWh
$443
-
kW-mo/yr
$(-603.0)
-
MMBtu
-
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $14,904 $12,900 $12,830
160,380
kWh
$5,739
-
kW-mo/yr
$(-3,665.0)
-
MMBtu
-
05 2.2437: Recover waste heat from equipment $10,676 $7,500 $7,566
94,578
kWh
$3,110
-
kW-mo/yr
- -
06 4.652: Replace existing equipment with more suitable substitutes $17,100 $12,300 - - - $17,100
TOTAL RECOMMENDED $74,747 $83,895 $36,519
456,492
kWh
$25,396
-
kW-mo/yr
$(-4,268.0)
-
MMBtu
$17,100
TOTAL IMPLEMENTED $33,158 $26,800 $14,144
176,800
kWh
$6,182
-
kW-mo/yr
$(-4,268.0)
-
MMBtu
$17,100
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs