Assessment Year | 1988 |
---|---|
Principal Product | WATER TREATMENT UNITS |
NAICS |
n/a
|
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
n/a
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $156,017 | 2,635,404 |
kWh
|
$0.059 |
Natural Gas | $50,142 | 11,108 |
MMBtu
|
$4.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $1,190 | - |
$1,190
20,223
kWh
|
- | - | |
02 | 2.6121: Reduce hot water temperature to the minimum required | $540 | - |
$540
9,086
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $926 | $1,257 |
$926
15,533
kWh
|
- | - | |
04 | 2.3191: Use demand controller or load shedder | $9,292 | - |
$9,792
-
kWh
|
- | $(-500.0) | |
05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,248 | $5,600 | - |
$3,248
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $15,196 | $6,857 |
$12,448
44,842
kWh
|
$3,248
-
MMBtu
|
$(-500.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs