ITAC Assessment: WI0008
ITAC logo
ITAC Assessment: WI0008
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product FAUCETS
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area
n/a
Annual Production 500,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $112,635 1,691,090
kWh
Natural Gas $63,957 13,479
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,855 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,730

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $562 - $562
8,499
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $269 - $269
4,103
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $644 $701 $644
9,672
kWh
- -
04 2.6121: Reduce hot water temperature to the minimum required $122 - $122
1,758
kWh
- -
05 2.3191: Use demand controller or load shedder $2,563 $5,000 $2,563
-
kWh
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $695 $500 - $945
-
MMBtu
$(-250.0)
TOTAL RECOMMENDED $4,855 $6,201 $4,160
24,032
kWh
$945
-
MMBtu
$(-250.0)
TOTAL IMPLEMENTED $1,730 $1,201 $1,035
15,533
kWh
$945
-
MMBtu
$(-250.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs