ITAC Assessment: WI0007
ITAC logo
ITAC Assessment: WI0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product WATER SOFTENER CONTROLS
NAICS
n/a
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area
n/a
Annual Production 150,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $64,599 945,780
kWh
Natural Gas $17,572 3,317
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,539 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,905

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $330 - $330
4,982
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $112 - $112
1,758
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,549 $5,631 $1,549
22,567
kWh
- -
04 2.6121: Reduce hot water temperature to the minimum required $129 - - $129
-
MMBtu
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $634 - $634
-
kWh
- -
06 2.1233: Analyze flue gas for proper air/fuel ratio $387 - - $387
-
MMBtu
-
07 2.1233: Analyze flue gas for proper air/fuel ratio $398 $500 - $498
-
MMBtu
$(-100.0)
TOTAL RECOMMENDED $3,539 $6,131 $2,625
29,307
kWh
$1,014
-
MMBtu
$(-100.0)
TOTAL IMPLEMENTED $2,905 $6,131 $1,991
29,307
kWh
$1,014
-
MMBtu
$(-100.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs