ITAC Assessment: WI0005
ITAC logo
ITAC Assessment: WI0005
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product SPECIALTY HAND TOOLS
NAICS
n/a
SIC 3423: Hand and Edge Tools, Except Machine Tools and Handsaws
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,125
hrs
Location (State) Wisconsin

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,349 1,433,763
kWh
Natural Gas $8,263 1,658
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,936

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4312: Improve lubrication practices $5,838 - $5,838
87,925
kWh
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,114 - $1,114
16,706
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $474 $110 $474
7,034
kWh
- -
04 2.4221: Install compressor air intakes in coolest locations $466 $620 $466
7,034
kWh
- -
05 2.3191: Use demand controller or load shedder $2,319 $2,700 $2,319
-
kWh
- -
06 2.1233: Analyze flue gas for proper air/fuel ratio $44 - - $384
-
MMBtu
$(-340.0)
TOTAL RECOMMENDED $10,255 $3,430 $10,211
118,699
kWh
$384
-
MMBtu
$(-340.0)
TOTAL IMPLEMENTED $7,936 $730 $7,892
118,699
kWh
$384
-
MMBtu
$(-340.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs