Assessment Year | 1987 |
---|---|
Principal Product | BUSHINGS & CYLIN. PARTS |
NAICS |
n/a
|
SIC | 3325: Steel Foundries, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 109 |
Plant Area |
n/a
|
Annual Production | 600,000
pieces
|
Production Hrs. Annual | 4,165
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,345 | 2,090,563 |
kWh
|
$0.061 |
Natural Gas | $21,000 | 3,920 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,004 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,343 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.4312: Improve lubrication practices | $11,988 | $3,268 |
$11,988
196,952
kWh
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,806 | - |
$2,806
46,014
kWh
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,776 | $3,998 |
$2,776
45,721
kWh
|
|
04 | 2.4221: Install compressor air intakes in coolest locations | $118 | $168 |
$118
2,052
kWh
|
|
05 | 2.3191: Use demand controller or load shedder | $2,543 | $3,000 |
$2,543
-
kWh
|
|
06 | 2.3212: Optimize plant power factor | $5,773 | $12,000 |
$5,773
-
kWh
|
|
TOTAL RECOMMENDED | $26,004 | $22,434 |
$26,004
290,739
kWh
|
||
TOTAL IMPLEMENTED | $23,343 | $19,266 |
$23,343
288,687
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs