| Assessment Year | 2026 |
|---|---|
| Principal Product | Concrete blocks, Stone masonry |
| NAICS | 212321: Construction Sand and Gravel Mining |
| SIC | 3271: Concrete Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 4 |
| Plant Area |
19,000
ft2
|
| Annual Production | 800,000
units
|
| Production Hrs. Annual | 1,890
hrs
|
| Location (State) | Alaska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $7,664 | 226,480 |
kWh
|
$0.034 |
| Electricity Demand | $51,780 | 1,561 |
kW-mo/yr
|
$33.17 |
| Electricity Fees | $20,232 | - |
|
- |
| Natural Gas | $31,003 | 3,307 |
MMBtu
|
$9.37 |
| Other Gas | $9,370 | 1 |
MMBtu
|
$9,370.00 |
| TOTAL YEARLY COSTS | $120,049 | |||
| RECOMMENDED SAVINGS* | $86,218 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings |
|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $1,400 | $1,080 |
$1,400
-
MMBtu
|
|
| 02 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $80,006 | $297,653 |
$80,006
-
MMBtu
|
|
| 03 | 2.2135: Repair and eliminate steam leaks | $4,812 | $3,250 |
$4,812
-
MMBtu
|
|
| TOTAL RECOMMENDED | $86,218 | $301,983 |
$86,218
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs