ITAC Assessment: UW2516
ITAC logo
ITAC Assessment: UW2516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product gravel aggregates
NAICS 212321: Construction Sand and Gravel Mining
SIC 1442: Construction Sand and Gravel
Sales Range $10
M
to 50
M
# of Employees 10
Plant Area 24,829,200
ft2
Annual Production 350,000
ton
Production Hrs. Annual 2,016
hrs
Location (State) Alaska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $299,304 1,668,534
kWh
Electricity Demand $73,946 8,416
kW-mo/yr
Electricity Fees $7,820 -
Waste Disposal Costs
Other Liquid (haz) $40,900 10,000
gal
TOTAL YEARLY COSTS $421,970
RECOMMENDED SAVINGS* $986,783 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.3191: Use demand controller or load shedder $64,296 $986,160 - $64,296
-
kW-mo/yr
- - -
02 2.4133: Use most efficient type of electric motors $22,966 $71,500 $22,966
128,016
kWh
- - - -
03 4.321: Optimize production lot sizes and inventories $884,000 $1,200,000 - - $52,501
-
gal
$32,000 $799,499
04 2.3212: Optimize plant power factor $15,521 $30,555 - $15,521
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $986,783 $2,288,215 $22,966
128,016
kWh
$79,817
-
kW-mo/yr
$52,501
-
gal
$32,000 $799,499
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs