| Assessment Year | 2026 |
|---|---|
| Principal Product | gravel aggregates |
| NAICS | 212321: Construction Sand and Gravel Mining |
| SIC | 1442: Construction Sand and Gravel |
| Sales Range | $10 M to 50M |
| # of Employees | 10 |
| Plant Area |
24,829,200
ft2
|
| Annual Production | 350,000
ton
|
| Production Hrs. Annual | 2,016
hrs
|
| Location (State) | Alaska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $299,304 | 1,668,534 |
kWh
|
$0.18 | |
| Electricity Demand | $73,946 | 8,416 |
kW-mo/yr
|
$8.79 | |
| Electricity Fees | $7,820 | - |
|
- | |
| Waste Disposal Costs | |||||
| Other Liquid (haz) | $40,900 | 10,000 |
gal
|
$4.09 | |
| TOTAL YEARLY COSTS | $421,970 | ||||
| RECOMMENDED SAVINGS* | $986,783 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $64,296 | $986,160 | - |
$64,296
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $22,966 | $71,500 |
$22,966
128,016
kWh
|
- | - | - | - | |
| 03 | 4.321: Optimize production lot sizes and inventories | $884,000 | $1,200,000 | - | - |
$52,501
-
gal
|
$32,000 | $799,499 | |
| 04 | 2.3212: Optimize plant power factor | $15,521 | $30,555 | - |
$15,521
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $986,783 | $2,288,215 |
$22,966
128,016
kWh
|
$79,817
-
kW-mo/yr
|
$52,501
-
gal
|
$32,000 | $799,499 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs