| Assessment Year | 2026 |
|---|---|
| Principal Product | gravel aggregates |
| NAICS | 212321: Construction Sand and Gravel Mining |
| SIC | 1442: Construction Sand and Gravel |
| Sales Range | $10 M to 50M |
| # of Employees | 10 |
| Plant Area |
24,829,200
ft2
|
| Annual Production | 350,000
ton
|
| Production Hrs. Annual | 2,016
hrs
|
| Location (State) | Alaska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $299,304 | 1,668,534 |
kWh
|
$0.18 |
| Electricity Demand | $73,946 | 8,416 |
kW-mo/yr
|
$8.79 |
| Electricity Fees | $7,820 | - |
|
- |
| Fuel Oil #1 | $306,930 | 10,356 |
MMBtu
|
$29.64 |
| TOTAL YEARLY COSTS | $688,000 | |||
| RECOMMENDED SAVINGS* | $213,447 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $15,521 | $30,555 | - |
$15,521
-
kW-mo/yr
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $47,926 | $139,500 |
$47,926
267,120
kWh
|
- | - | - | |
| 03 | 4.321: Optimize production lot sizes and inventories | $150,000 | $1,200,000 | - | - |
$52,501
-
MMBtu
|
$97,499 | |
| TOTAL RECOMMENDED | $213,447 | $1,370,055 |
$47,926
267,120
kWh
|
$15,521
-
kW-mo/yr
|
$52,501
-
MMBtu
|
$97,499 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs