ITAC Assessment: UW2505
ITAC logo
ITAC Assessment: UW2505
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Aerospace Manufacturing
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 239
Plant Area 106,857
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $368,394 4,221,600
kWh
Electricity Fees $19,389 -
Natural Gas $69,724 7,700
MMBtu
TOTAL YEARLY COSTS $457,507
RECOMMENDED SAVINGS* $139,874 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,747 $15,000 $31,747
352,745
kWh
-
02 2.2113: Repair or replace steam traps $30,117 $4,550 - $30,117
-
MMBtu
03 2.7232: Replace existing hvac unit with high efficiency model $20,963 $191,676 $(-14,433.0)
(-157,125)
kWh
$35,396
-
MMBtu
04 4.662: Level one – add communication using iiot devices to existing control system to modify operations $55,282 $123,500 $55,282
633,240
kWh
-
05 2.2123: Insulate feedwater tank $815 $443 - $815
-
MMBtu
06 2.2515: Use optimum thickness insulation $950 $3,710 - $950
-
MMBtu
TOTAL RECOMMENDED $139,874 $338,879 $72,596
828,860
kWh
$67,278
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs