Assessment Year | 2025 |
---|---|
Principal Product | Water and Sewer Utility Service |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
134,000
ft2
|
Annual Production | 1,500,000
Tgal
|
Production Hrs. Annual | 2,470
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,853 | 278,021 |
kWh
|
$0.089 |
Electricity Demand | $1,128 | 1,281 |
kW-mo/yr
|
$0.88 |
Electricity Fees | $1,605 | - |
|
- |
Natural Gas | $13,747 | 1,014 |
MMBtu
|
$13.56 |
TOTAL YEARLY COSTS | $41,333 | |||
RECOMMENDED SAVINGS* | $21,274 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7492: Use proper thickness of insulation on building envelope | $2,373 | $13,260 | - | - |
$2,373
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $332 | $2,872 |
$332
3,728
kWh
|
$0
-
kW-mo/yr
|
- | |
03 | 2.8226: Increase efficiency of trucks | $10,938 | $114,250 |
$10,938
122,353
kWh
|
- | - | |
04 | 2.9114: Use solar heat to make electricty | $5,248 | $31,835 |
$5,248
58,713
kWh
|
- | - | |
05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $2,383 | $20,158 |
$2,359
26,385
kWh
|
$24
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $21,274 | $182,375 |
$18,877
211,179
kWh
|
$24
-
kW-mo/yr
|
$2,373
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs