| Assessment Year | 2004 |
|---|---|
| Principal Product | Elemental Iodine |
| NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
| SIC | 2864: |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
803,000
ft2
|
| Annual Production | 4,200
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,413,850 | 43,851,840 |
kWh
|
$0.032 |
| Electricity Demand | $346,646 | 66,633 |
kW-mo/yr
|
$5.20 |
| Electricity Fees | $7,644 | - |
|
- |
| LPG | $98,199 | 8,116 |
MMBtu
|
$12.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,183,091 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,404 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $1,045,517 | $1,029,484 |
$(-3,667.0)
(-79,716)
kWh
|
$(-816.0)
-
kW-mo/yr
|
- | - | - | $1,050,000 | |
| 02 | 2.1331: Burn a less expensive grade of fuel | $60,059 | $691 | - | - |
$(-38,145.0)
-
MMBtu
|
$98,204
-
MMBtu
|
- | - | |
| 03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $9,026 | $9,344 |
$6,241
193,833
kWh
|
$2,785
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $65,085 | $407,420 |
$53,269
1,654,330
kWh
|
$11,816
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.2511: Insulate bare equipment | $2,247 | $2,094 | - | - | - |
$2,247
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,157 | $2,968 |
$554
17,192
kWh
|
$368
-
kW-mo/yr
|
- | - | $235 | - | |
| TOTAL RECOMMENDED | $1,183,091 | $1,452,001 |
$56,397
1,785,639
kWh
|
$14,153
-
kW-mo/yr
|
$(-38,145.0)
-
MMBtu
|
$100,451
-
MMBtu
|
$235 | $1,050,000 | ||
| TOTAL IMPLEMENTED | $3,404 | $5,062 |
$554
17,192
kWh
|
$368
-
kW-mo/yr
|
- |
$2,247
-
MMBtu
|
$235 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs