Assessment Year | 2023 |
---|---|
Principal Product | Apples, Cherries, Pears |
NAICS | 111331: Apple Orchards |
SIC | 0175: Deciduous Tree Fruits |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
530,000
ft2
|
Annual Production | 518,750,000
lb
|
Production Hrs. Annual | 7,644
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $298,411 | 20,574,812 |
kWh
|
$0.015 | |
Electricity Demand | $117,979 | 33,231 |
kW-mo/yr
|
$3.55 | |
Electricity Fees | $31,921 | - |
|
- | |
Natural Gas | $100,443 | 10,665 |
MMBtu
|
$9.42 | |
Waste Disposal Costs | |||||
Water Usage | $379,765 | 52,711 |
Tgal
|
$7.20 | |
TOTAL YEARLY COSTS | $928,519 | ||||
RECOMMENDED SAVINGS* | $345,806 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $345,430 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $345,363 | $28,215 | - | - |
$345,363
-
Tgal
|
|
02 | 2.7135: Install occupancy sensors | $67 | $180 |
$67
4,673
kWh
|
- | - | |
03 | 2.4321: Upgrade obsolete equipment | $376 | $5,862 |
$231
15,940
kWh
|
$145
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $345,806 | $34,257 |
$298
20,613
kWh
|
$145
-
kW-mo/yr
|
$345,363
-
Tgal
|
||
TOTAL IMPLEMENTED | $345,430 | $28,395 |
$67
4,673
kWh
|
- |
$345,363
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs