ITAC Assessment: UW2317
ITAC logo
ITAC Assessment: UW2317
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Warm Mix and Hot Mix Asphalt
NAICS 327320: Ready-Mix Concrete Manufacturing
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 13
Plant Area 6,065
ft2
Annual Production 250,000
ton
Production Hrs. Annual 2,904
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,886 715,977
kWh
Electricity Demand $18,224 3,672
kW-mo/yr
Electricity Fees $13,097 -
Natural Gas $244,371 40,379
MMBtu
TOTAL YEARLY COSTS $336,578
RECOMMENDED SAVINGS* $63,207 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,207

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $533 - $410
4,823
kWh
$123
-
kW-mo/yr
-
02 2.7243: Improve air circulation with destratification fans / other methods $658 $1,096 $658
7,739
kWh
- -
03 2.7494: Install storm windows and doors $156 $1,901 $142
1,647
kWh
$14
-
kW-mo/yr
-
04 2.5195: Change product design to reduce energy requirements $31,756 $1,000,000 - - $31,756
-
MMBtu
05 2.1116: Improve combustion control capability $30,104 $300,000 - - $30,104
-
MMBtu
TOTAL RECOMMENDED $63,207 $1,302,997 $1,210
14,209
kWh
$137
-
kW-mo/yr
$61,860
-
MMBtu
TOTAL IMPLEMENTED $63,207 $1,302,997 $1,210
14,209
kWh
$137
-
kW-mo/yr
$61,860
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs