Assessment Year | 2023 |
---|---|
Principal Product | Warm Mix and Hot Mix Asphalt |
NAICS | 327320: Ready-Mix Concrete Manufacturing |
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $10 M to 50M |
# of Employees | 13 |
Plant Area |
6,065
ft2
|
Annual Production | 250,000
ton
|
Production Hrs. Annual | 2,904
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,886 | 715,977 |
kWh
|
$0.085 |
Electricity Demand | $18,224 | 3,672 |
kW-mo/yr
|
$4.96 |
Electricity Fees | $13,097 | - |
|
- |
Natural Gas | $244,371 | 40,379 |
MMBtu
|
$6.05 |
TOTAL YEARLY COSTS | $336,578 | |||
RECOMMENDED SAVINGS* | $63,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $63,207 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $533 | - |
$410
4,823
kWh
|
$123
-
kW-mo/yr
|
- | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $658 | $1,096 |
$658
7,739
kWh
|
- | - | |
03 | 2.7494: Install storm windows and doors | $156 | $1,901 |
$142
1,647
kWh
|
$14
-
kW-mo/yr
|
- | |
04 | 2.5195: Change product design to reduce energy requirements | $31,756 | $1,000,000 | - | - |
$31,756
-
MMBtu
|
|
05 | 2.1116: Improve combustion control capability | $30,104 | $300,000 | - | - |
$30,104
-
MMBtu
|
|
TOTAL RECOMMENDED | $63,207 | $1,302,997 |
$1,210
14,209
kWh
|
$137
-
kW-mo/yr
|
$61,860
-
MMBtu
|
||
TOTAL IMPLEMENTED | $63,207 | $1,302,997 |
$1,210
14,209
kWh
|
$137
-
kW-mo/yr
|
$61,860
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs