| Assessment Year | 2023 |
|---|---|
| Principal Product | Warm Mix and Hot Mix Asphalt |
| NAICS | 327320: Ready-Mix Concrete Manufacturing |
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $10 M to 50M |
| # of Employees | 13 |
| Plant Area |
6,065
ft2
|
| Annual Production | 250,000
ton
|
| Production Hrs. Annual | 2,904
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $60,886 | 715,977 |
kWh
|
$0.085 |
| Electricity Demand | $18,224 | 3,672 |
kW-mo/yr
|
$4.96 |
| Electricity Fees | $13,097 | - |
|
- |
| Natural Gas | $244,371 | 40,379 |
MMBtu
|
$6.05 |
| TOTAL YEARLY COSTS | $336,578 | |||
| RECOMMENDED SAVINGS* | $63,207 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,207 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $533 | - |
$410
4,823
kWh
|
$123
-
kW-mo/yr
|
- | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $658 | $1,096 |
$658
7,739
kWh
|
- | - | |
| 03 | 2.7494: Install storm windows and doors | $156 | $1,901 |
$142
1,647
kWh
|
$14
-
kW-mo/yr
|
- | |
| 04 | 2.5195: Change product design to reduce energy requirements | $31,756 | $1,000,000 | - | - |
$31,756
-
MMBtu
|
|
| 05 | 2.1116: Improve combustion control capability | $30,104 | $300,000 | - | - |
$30,104
-
MMBtu
|
|
| TOTAL RECOMMENDED | $63,207 | $1,302,997 |
$1,210
14,209
kWh
|
$137
-
kW-mo/yr
|
$61,860
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $63,207 | $1,302,997 |
$1,210
14,209
kWh
|
$137
-
kW-mo/yr
|
$61,860
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs