| Assessment Year | 2023 |
|---|---|
| Principal Product | batch/mix plants in manufacturing concrete. |
| NAICS | 327320: Ready-Mix Concrete Manufacturing |
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $10 M to 50M |
| # of Employees | 5 |
| Plant Area |
6,065
ft2
|
| Annual Production | 600,000
ton
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $142,700 | 1,731,990 |
kWh
|
$0.082 |
| Electricity Demand | $81,279 | 13,510 |
kW-mo/yr
|
$6.02 |
| Electricity Fees | $45,061 | - |
|
- |
| Natural Gas | $24,956 | 4,181 |
MMBtu
|
$5.97 |
| TOTAL YEARLY COSTS | $293,996 | |||
| RECOMMENDED SAVINGS* | $37,636 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,293 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7243: Improve air circulation with destratification fans / other methods | $6,189 | $1,896 |
$6,189
75,202
kWh
|
- | - | |
| 02 | 2.1116: Improve combustion control capability | $30,104 | $300,000 | - | - |
$30,104
-
MMBtu
|
|
| 03 | 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses | $1,343 | $10,879 |
$1,211
14,709
kWh
|
$132
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $37,636 | $312,775 |
$7,400
89,911
kWh
|
$132
-
kW-mo/yr
|
$30,104
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $36,293 | $301,896 |
$6,189
75,202
kWh
|
- |
$30,104
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs