ITAC Assessment: UW2311
ITAC logo
ITAC Assessment: UW2311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Other Aircraft Parts and Auxiliary Equipment Manufacturing
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 268
Plant Area 20,000
ft2
Annual Production 50,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $285,992 3,942,700
kWh
Electricity Demand $85,037 15,489
kW-mo/yr
Electricity Fees $19,109 -
Natural Gas $63,355 7,658
MMBtu
TOTAL YEARLY COSTS $453,493
RECOMMENDED SAVINGS* $157,389 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $157,389

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7232: Replace existing hvac unit with high efficiency model $6,427 $15,722 $(-2,009.0)
(-27,716)
kWh
$(-694.0)
-
kW-mo/yr
$9,130
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $26,668 $83,148 $24,162
333,267
kWh
$2,506
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $470 $2,080 $426
5,876
kWh
$44
-
kW-mo/yr
-
04 2.9114: Use solar heat to make electricty $112,574 $693,588 $101,994
1,406,815
kWh
$10,580
-
kW-mo/yr
-
05 2.3212: Optimize plant power factor $11,250 $49,905 - $11,250
-
kW-mo/yr
-
TOTAL RECOMMENDED $157,389 $844,443 $124,573
1,718,242
kWh
$23,686
-
kW-mo/yr
$9,130
-
MMBtu
TOTAL IMPLEMENTED $157,389 $844,443 $124,573
1,718,242
kWh
$23,686
-
kW-mo/yr
$9,130
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs