| Assessment Year | 2023 |
|---|---|
| Principal Product | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
88,000
ft2
|
| Annual Production | 682,892
units
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $128,327 | 1,775,100 |
kWh
|
$0.072 |
| Electricity Demand | $25,975 | 4,942 |
kW-mo/yr
|
$5.26 |
| Electricity Fees | $9,620 | - |
|
- |
| Natural Gas | $105,774 | 9,561 |
MMBtu
|
$11.06 |
| LPG | $1,798 | 77 |
MMBtu
|
$23.35 |
| TOTAL YEARLY COSTS | $271,494 | |||
| RECOMMENDED SAVINGS* | $196,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,635 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2314: Replace heat treating oven with more efficient unit | $29,254 | $128,809 | - | - |
$29,254
-
MMBtu
|
- | |
| 02 | 2.4321: Upgrade obsolete equipment | $153,154 | $859,050 |
$2,776
38,556
kWh
|
$378
-
kW-mo/yr
|
- | $150,000 | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,425 | $1,000 |
$3,109
43,183
kWh
|
$316
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,210 | $16,378 |
$9,190
103,494
kWh
|
$1,020
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $196,043 | $1,005,237 |
$15,075
185,233
kWh
|
$1,714
-
kW-mo/yr
|
$29,254
-
MMBtu
|
$150,000 | ||
| TOTAL IMPLEMENTED | $13,635 | $17,378 |
$12,299
146,677
kWh
|
$1,336
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs