ITAC Assessment: UW2310
ITAC logo
ITAC Assessment: UW2310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Other Aircraft Parts and Auxiliary Equipment Manufacturing
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 88,000
ft2
Annual Production 682,892
units
Production Hrs. Annual 6,864
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $128,327 1,775,100
kWh
Electricity Demand $25,975 4,942
kW-mo/yr
Electricity Fees $9,620 -
Natural Gas $105,774 9,561
MMBtu
LPG $1,798 77
MMBtu
TOTAL YEARLY COSTS $271,494
RECOMMENDED SAVINGS* $196,043 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,635

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Increase in Production Savings
01 2.2314: Replace heat treating oven with more efficient unit $29,254 $128,809 - - $29,254
-
MMBtu
-
02 2.4321: Upgrade obsolete equipment $153,154 $859,050 $2,776
38,556
kWh
$378
-
kW-mo/yr
- $150,000
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,425 $1,000 $3,109
43,183
kWh
$316
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $10,210 $16,378 $9,190
103,494
kWh
$1,020
-
kW-mo/yr
- -
TOTAL RECOMMENDED $196,043 $1,005,237 $15,075
185,233
kWh
$1,714
-
kW-mo/yr
$29,254
-
MMBtu
$150,000
TOTAL IMPLEMENTED $13,635 $17,378 $12,299
146,677
kWh
$1,336
-
kW-mo/yr
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs