Assessment Year | 2023 |
---|---|
Principal Product | Other Aircraft Parts and Auxiliary Equipment Manufacturing |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
88,000
ft2
|
Annual Production | 682,892
units
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $128,327 | 1,775,100 |
kWh
|
$0.072 |
Electricity Demand | $25,975 | 4,942 |
kW-mo/yr
|
$5.26 |
Electricity Fees | $9,620 | - |
|
- |
Natural Gas | $105,774 | 9,561 |
MMBtu
|
$11.06 |
LPG | $1,798 | 77 |
MMBtu
|
$23.35 |
TOTAL YEARLY COSTS | $271,494 | |||
RECOMMENDED SAVINGS* | $196,043 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2314: Replace heat treating oven with more efficient unit | $29,254 | $128,809 | - | - |
$29,254
-
MMBtu
|
- | |
02 | 2.4321: Upgrade obsolete equipment | $153,154 | $859,050 |
$2,776
38,556
kWh
|
$378
-
kW-mo/yr
|
- | $150,000 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,425 | $1,000 |
$3,109
43,183
kWh
|
$316
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,210 | $16,378 |
$9,190
103,494
kWh
|
$1,020
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $196,043 | $1,005,237 |
$15,075
185,233
kWh
|
$1,714
-
kW-mo/yr
|
$29,254
-
MMBtu
|
$150,000 | ||
TOTAL IMPLEMENTED | $13,635 | $17,378 |
$12,299
146,677
kWh
|
$1,336
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs