| Assessment Year | 2022 |
|---|---|
| Principal Product | Motorcycle, Bicycle, and Parts Manufacturing |
| NAICS | 336991: Motorcycle, Bicycle, and Parts Manufacturing |
| SIC | 3751: Motorcycles, Bicycles, and Parts |
| Sales Range | $10 M to 50M |
| # of Employees | 49 |
| Plant Area |
54,000
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 2,262
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,505 | 369,575 |
kWh
|
$0.13 |
| Electricity Demand | $16,879 | 3,136 |
kW-mo/yr
|
$5.38 |
| Natural Gas | $32,268 | 4,389 |
MMBtu
|
$7.35 |
| LPG | $1,843 | 77 |
MMBtu
|
$24.06 |
| TOTAL YEARLY COSTS | $100,495 | |||
| RECOMMENDED SAVINGS* | $5,209 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,351 | $2,080 |
$1,114
8,315
kWh
|
$237
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $843 | $970 |
$843
6,293
kWh
|
- | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $3,014 | - | - | - |
$3,014
-
MMBtu
|
|
| TOTAL RECOMMENDED | $5,209 | $3,050 |
$1,957
14,608
kWh
|
$237
-
kW-mo/yr
|
$3,014
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs