*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Wine
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 40,000
ft2
Annual Production 50
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,236 2,560,884
kWh
Electricity Demand $41,434 11,618
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $0.0 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $0.0

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 4.821: Pay bills on time to avoid late fees $0.0 - $0.0
1
kWh
TOTAL RECOMMENDED $0.0 - $0.0
1
kWh
TOTAL IMPLEMENTED $0.0 - $0.0
1
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs