ITAC Assessment: UW0036
ITAC logo
ITAC Assessment: UW0036
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Frozen Seafood
NAICS 311412: Frozen Specialty Food Manufacturing
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 28
Plant Area 40,000
ft2
Annual Production 1,100,000
lb
Production Hrs. Annual 5,304
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,318 451,200
kWh
Electricity Demand $6,394 1,464
kW-mo/yr
Natural Gas $1,488 143
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.2622: Replace existing chiller with high efficiency model $30,860 $61,720 $27,465
309,213
kWh
$3,395
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,120 $1,590 $3,589
40,416
kWh
$531
-
kW-mo/yr
-
03 2.3212: Optimize plant power factor $1,039 $1,072 - - $1,039
04 4.821: Pay bills on time to avoid late fees $819 $45 - - $819
05 2.4133: Use most efficient type of electric motors $417 $825 $363
4,087
kWh
$54
-
kW-mo/yr
-
TOTAL RECOMMENDED $37,255 $65,252 $31,417
353,716
kWh
$3,980
-
kW-mo/yr
$1,858
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs