| Assessment Year | 2009 |
|---|---|
| Principal Product | Sheet Metal Products |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
100,000
ft2
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $72,084 | 1,463,960 |
kWh
|
$0.049 |
| Natural Gas | $37,836 | 2,825 |
MMBtu
|
$13.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,587 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,787 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $8,800 | $7,248 |
$650
13,009
kWh
|
- |
$8,150
-
MMBtu
|
|
| 02 | 2.4133: Use most efficient type of electric motors | $8,782 | $31,747 |
$8,320
178,523
kWh
|
$462
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,643 | $10,000 |
$3,439
73,169
kWh
|
$204
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,065 | $3,070 |
$4,799
95,986
kWh
|
$266
-
kW-mo/yr
|
- | |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $297 | $200 | - | - |
$297
-
MMBtu
|
|
| TOTAL RECOMMENDED | $26,587 | $52,265 |
$17,208
360,687
kWh
|
$932
-
kW-mo/yr
|
$8,447
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,787 | $45,017 |
$16,558
347,678
kWh
|
$932
-
kW-mo/yr
|
$297
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs