| Assessment Year | 2008 |
|---|---|
| Principal Product | Metal Tubing |
| NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
78,000
ft2
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 7,176
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $88,052 | 1,386,600 |
kWh
|
$0.064 |
| Electricity Demand | $26,682 | 3,853 |
kW-mo/yr
|
$6.92 |
| Electricity Fees | $2,216 | - |
|
- |
| Natural Gas | $121,586 | 11,555 |
MMBtu
|
$10.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,608 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,074 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1224: Replace boiler | $16,074 | $25,870 | - | - |
$16,074
-
MMBtu
|
- | |
| 02 | 2.2511: Insulate bare equipment | $15,042 | $2,500 | - | - |
$15,042
-
MMBtu
|
- | |
| 03 | 2.2511: Insulate bare equipment | $14,046 | $2,908 | - | - |
$12,230
-
MMBtu
|
$1,816
-
Tgal
|
|
| 04 | 2.7135: Install occupancy sensors | $4,446 | $2,439 |
$3,822
63,261
kWh
|
$624
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $49,608 | $33,717 |
$3,822
63,261
kWh
|
$624
-
kW-mo/yr
|
$43,346
-
MMBtu
|
$1,816
-
Tgal
|
||
| TOTAL IMPLEMENTED | $16,074 | $25,870 | - | - |
$16,074
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs