Assessment Year | 2008 |
---|---|
Principal Product | Metal Tubing |
NAICS | 331110: Iron and Steel Mills and Ferroalloy Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
78,000
ft2
|
Annual Production | 50,000
pieces
|
Production Hrs. Annual | 7,176
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $88,052 | 1,386,600 |
kWh
|
$0.064 |
Electricity Demand | $26,682 | 3,853 |
kW-mo/yr
|
$6.92 |
Electricity Fees | $2,216 | - |
|
- |
Natural Gas | $121,586 | 11,555 |
MMBtu
|
$10.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,608 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,074 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1224: Replace boiler | $16,074 | $25,870 | - | - |
$16,074
-
MMBtu
|
- | |
02 | 2.2511: Insulate bare equipment | $15,042 | $2,500 | - | - |
$15,042
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $14,046 | $2,908 | - | - |
$12,230
-
MMBtu
|
$1,816
-
Tgal
|
|
04 | 2.7135: Install occupancy sensors | $4,446 | $2,439 |
$3,822
63,261
kWh
|
$624
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $49,608 | $33,717 |
$3,822
63,261
kWh
|
$624
-
kW-mo/yr
|
$43,346
-
MMBtu
|
$1,816
-
Tgal
|
||
TOTAL IMPLEMENTED | $16,074 | $25,870 | - | - |
$16,074
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs