ITAC Assessment: UW0019
ITAC logo
ITAC Assessment: UW0019
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Metal Tubing
NAICS 331110: Iron and Steel Mills and Ferroalloy Manufacturing
SIC 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 78,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 7,176
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $88,052 1,386,600
kWh
Electricity Demand $26,682 3,853
kW-mo/yr
Electricity Fees $2,216 -
Natural Gas $121,586 11,555
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,608 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,074

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.1224: Replace boiler $16,074 $25,870 - - $16,074
-
MMBtu
-
02 2.2511: Insulate bare equipment $15,042 $2,500 - - $15,042
-
MMBtu
-
03 2.2511: Insulate bare equipment $14,046 $2,908 - - $12,230
-
MMBtu
$1,816
-
Tgal
04 2.7135: Install occupancy sensors $4,446 $2,439 $3,822
63,261
kWh
$624
-
kW-mo/yr
- -
TOTAL RECOMMENDED $49,608 $33,717 $3,822
63,261
kWh
$624
-
kW-mo/yr
$43,346
-
MMBtu
$1,816
-
Tgal
TOTAL IMPLEMENTED $16,074 $25,870 - - $16,074
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs