ITAC Assessment: AM0931
ITAC logo
ITAC Assessment: AM0931
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product School students
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area 90,775
ft2
Annual Production 150
units
Production Hrs. Annual 2,850
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,597 857,805
kWh
Electricity Demand $37,175 3,390
kW-mo/yr
Natural Gas $7,910 776
MMBtu
TOTAL YEARLY COSTS $77,682
RECOMMENDED SAVINGS* $32,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,952 $48,006 $4,148
109,158
kWh
$6,804
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $2,803 $8,670 $2,803
73,754
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $161 $1,000 $161
4,244
kWh
- -
04 3.7311: Maintain machines to reduce leaks $197 $65 $197
5,178
kWh
- -
05 2.9114: Use solar heat to make electricty $18,321 $499,200 $18,321
482,124
kWh
- -
06 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses $147 $4,226 $76
1,987
kWh
- $71
-
MMBtu
TOTAL RECOMMENDED $32,581 $561,167 $25,706
676,445
kWh
$6,804
-
kW-mo/yr
$71
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs