ITAC Assessment: UW0016
ITAC logo
ITAC Assessment: UW0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Tofu and Tofu Products
NAICS 311999: All Other Miscellaneous Food Manufacturing
SIC 2099: Food Preparations, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 22
Plant Area 10,000
ft2
Annual Production 540,000
lb
Production Hrs. Annual 3,510
hrs
Location (State) Hawaii

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,635 73,415
kWh
Electricity Demand $1,718 300
kW-mo/yr
Natural Gas $82,543 2,419
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $41,263

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.8114: Change rate schedules or other changes in utility service $29,638 - - - $29,638
-
MMBtu
-
02 2.1224: Replace boiler $10,000 $20,000 - - $10,000
-
MMBtu
-
03 2.2113: Repair or replace steam traps $5,490 $5,600 - - $5,490
-
MMBtu
-
04 2.2511: Insulate bare equipment $7,000 $500 - - $7,000
-
MMBtu
-
05 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $4,625 $8,550 $4,608
24,255
kWh
$17
-
kW-mo/yr
- -
06 3.4156: Use flow control valves on equipment to optimize water use $5,510 $10 - - - $5,510
-
Tgal
07 2.4231: Reduce the pressure of compressed air to the minimum required $892 - $808
4,255
kWh
$84
-
kW-mo/yr
- -
TOTAL RECOMMENDED $63,155 $34,660 $5,416
28,510
kWh
$101
-
kW-mo/yr
$52,128
-
MMBtu
$5,510
-
Tgal
TOTAL IMPLEMENTED $41,263 $9,050 $4,608
24,255
kWh
$17
-
kW-mo/yr
$36,638
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs