ITAC Assessment: GT0863
ITAC logo
ITAC Assessment: GT0863
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Airfoils
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $100
M
to 500
M
# of Employees 700
Plant Area 170,000
ft2
Annual Production 3,200,000
lb
Production Hrs. Annual 8,424
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,031,671 24,563,588
kWh
Electricity Demand $457,702 39,974
kW-mo/yr
Electricity Fees $1,073 -
Natural Gas $2,006,474 117,276
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $646,936 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.2135: Repair and eliminate steam leaks $3,847 $500 - - $3,847
-
MMBtu
-
02 4.812: Apply for investment incentives $24,150 - - - - $24,150
03 2.4322: Use or replace with energy efficient substitutes $194,835 $180,000 $131,164
3,122,945
kWh
$63,671
-
kW-mo/yr
- -
04 2.2414: Use waste heat from hot flue gases to preheat $316,142 $180,000 - - $316,142
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $107,962 $125,000 - - $107,962
-
MMBtu
-
TOTAL RECOMMENDED $646,936 $485,500 $131,164
3,122,945
kWh
$63,671
-
kW-mo/yr
$427,951
-
MMBtu
$24,150
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs