ITAC Assessment: UW0011
ITAC logo
ITAC Assessment: UW0011
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Wine
NAICS 312130: Wineries
SIC 2084: Wines, Brandy, and Brandy Spirits
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 30,450
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 4,680
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $61,922 926,760
kWh
Electricity Demand $16,223 2,465
kW-mo/yr
Electricity Fees $1,598 -
Natural Gas $29,709 2,539
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $37,096 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.1224: Replace boiler $8,882 $23,870 - - $8,882
-
MMBtu
-
02 2.2511: Insulate bare equipment $7,908 $15,906 $7,908
130,903
kWh
- - -
03 3.6125: Sell combustible waste $5,774 - - - - $5,774
-
lb
04 2.9112: Use solar heat to heat water $5,523 $20,275 - - $5,523
-
MMBtu
-
05 2.7145: Install skylights $5,089 $26,250 $4,464
63,540
kWh
$625
-
kW-mo/yr
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $2,444 - $1,979
32,760
kWh
$465
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $1,476 $300 $1,476
20,152
kWh
- - -
TOTAL RECOMMENDED $37,096 $86,601 $15,827
247,355
kWh
$1,090
-
kW-mo/yr
$14,405
-
MMBtu
$5,774
-
lb
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs