| Assessment Year | 2007 |
|---|---|
| Principal Product | Ship Building and Repairing |
| NAICS | 336611: Ship Building and Repairing |
| SIC | 3731: Ship Building and Repairing |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
60,000
ft2
|
| Annual Production | 50
units
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $156,288 | 2,971,500 |
kWh
|
$0.053 |
| Electricity Demand | $8,185 | 7,947 |
kW-mo/yr
|
$1.03 |
| Electricity Fees | $2,895 | - |
|
- |
| Natural Gas | $32,436 | 2,546 |
MMBtu
|
$12.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,040 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,468 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $15,370 | $62,800 |
$15,370
318,423
kWh
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,257 | $3,146 |
$1,211
25,938
kWh
|
$46
-
kW-mo/yr
|
- | |
| 03 | 2.9114: Use solar heat to make electricty | $1,315 | $585 | - | - | $1,315 | |
| 04 | 2.7135: Install occupancy sensors | $98 | $355 |
$96
2,051
kWh
|
$2
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $18,040 | $66,886 |
$16,677
346,412
kWh
|
$48
-
kW-mo/yr
|
$1,315 | ||
| TOTAL IMPLEMENTED | $15,468 | $63,155 |
$15,466
320,474
kWh
|
$2
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs