| Assessment Year | 2025 |
|---|---|
| Principal Product | Farm Machinery and Equipment |
| NAICS | 333111: Farm Machinery and Equipment Manufacturing |
| SIC | 3523: Farm Machinery and Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 485 |
| Plant Area |
375,000
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 5,684
hrs
|
| Location (State) | Idaho |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $190,040 | 4,275,121 |
kWh
|
$0.044 |
| Electricity Demand | $127,369 | 11,525 |
kW-mo/yr
|
$11.05 |
| Electricity Fees | $42,262 | - |
|
- |
| Natural Gas | $173,687 | 45,680 |
MMBtu
|
$3.80 |
| TOTAL YEARLY COSTS | $533,358 | |||
| RECOMMENDED SAVINGS* | $960,408 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.631: Install an uninteruptable power supply | $915,000 | $1,225,000 | - | - | - | $915,000 | |
| 02 | 2.7231: Use radiant heater for spot heating | $20,650 | $49,320 | - | - |
$20,650
-
MMBtu
|
- | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,600 | $15,750 | - |
$7,600
-
kW-mo/yr
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $13,143 | $47,180 | - | - |
$13,143
-
MMBtu
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $1,312 | $5,310 |
$(-210.0)
(-4,762)
kWh
|
- |
$1,522
-
MMBtu
|
- | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $2,703 | $6,732 |
$1,995
45,335
kWh
|
$708
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $960,408 | $1,349,292 |
$1,785
40,573
kWh
|
$8,308
-
kW-mo/yr
|
$35,315
-
MMBtu
|
$915,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs