Assessment Year | 2025 |
---|---|
Principal Product | Machine Parts and Fabricated Metals |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
30,000
ft2
|
Annual Production | 784,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $122,293 | 1,995,160 |
kWh
|
$0.061 |
Electricity Demand | $76,101 | 4,485 |
kW-mo/yr
|
$16.97 |
TOTAL YEARLY COSTS | $198,394 | |||
RECOMMENDED SAVINGS* | $67,313 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.2628: Utilize a less expensive cooling method | $21,325 | $74,279 |
$15,369
250,717
kWh
|
$5,956
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $8,865 | $7,100 |
$7,754
127,113
kWh
|
$1,111
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $5,305 | $5,305 |
$2,652
43,474
kWh
|
$2,653
-
kW-mo/yr
|
- | |
04 | 2.3212: Optimize plant power factor | $4,000 | $12,788 | - | - | $4,000 | |
05 | 2.9114: Use solar heat to make electricty | $27,818 | $116,050 |
$26,230
430,000
kWh
|
$1,588
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $67,313 | $215,522 |
$52,005
851,304
kWh
|
$11,309
-
kW-mo/yr
|
$4,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs