ITAC Assessment: UU0274
ITAC logo
ITAC Assessment: UU0274
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product N/A
NAICS 921120: Legislative Bodies
SIC 8221: Colleges, Universities, and Professional Schools
Sales Range less than $500
k
# of Employees 300
Plant Area 205,000
ft2
Annual Production 1
units
Production Hrs. Annual 3,650
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $151,046 3,269,400
kWh
Electricity Demand $126,540 8,664
kW-mo/yr
Electricity Fees $399 -
Waste Disposal Costs
Water Usage $3,965 1,035
Tgal
Water Disposal $5,807 264
Tgal
TOTAL YEARLY COSTS $287,757
RECOMMENDED SAVINGS* $190,842 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7311: Ventilation system to shut off when room is not in use $15,524 $18,000 $5,230
113,270
kWh
$10,294
-
kW-mo/yr
02 2.9114: Use solar heat to make electricty $155,368 $3,150,000 $102,795
2,250,300
kWh
$52,573
-
kW-mo/yr
03 2.7224: Reduce space conditioning during non-working hours $13,000 $7,200 $13,000
281,000
kWh
-
04 2.7221: Lower temperature during the winter season and vice-versa $6,950 $7,200 $6,950
150,540
kWh
-
TOTAL RECOMMENDED $190,842 $3,182,400 $127,975
2,795,110
kWh
$62,867
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs