| Assessment Year | 2025 |
|---|---|
| Principal Product | Image Generators |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 134 |
| Plant Area |
113,000
ft2
|
| Annual Production | 125
units
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $84,467 | 2,309,708 |
kWh
|
$0.037 | |
| Electricity Demand | $49,601 | 4,210 |
kW-mo/yr
|
$11.78 | |
| Electricity Fees | $68,175 | - |
|
- | |
| Natural Gas | $37,660 | 3,355 |
MMBtu
|
$11.23 | |
| Waste Disposal Costs | |||||
| Water Usage | $23,355 | 3,882 |
Tgal
|
$6.02 | |
| Water Disposal | $19,062 | 1,848 |
Tgal
|
$10.31 | |
| TOTAL YEARLY COSTS | $282,319 | ||||
| RECOMMENDED SAVINGS* | $16,849 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2611: Moderate cooling tower outlet temperature | $3,038 | $1,248 |
$2,092
57,201
kWh
|
$946
-
kW-mo/yr
|
- | - | |
| 02 | 2.2625: Chill water to the highest temperature possible | $133 | $1,175 |
$133
3,630
kWh
|
- | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,296 | $11,327 |
$3,296
90,133
kWh
|
- | - | - | |
| 04 | 3.4151: Minimize water usage | $3,231 | $23,282 | - | - |
$3,231
-
Tgal
|
- | |
| 05 | 3.4154: Eliminate leaks in water lines and valves | $771 | $5,877 | - | - |
$771
-
Tgal
|
- | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $6,046 | $20,000 | - | - | - | $6,046 | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $335 | $648 |
$211
5,761
kWh
|
$124
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $16,849 | $63,557 |
$5,731
156,725
kWh
|
$1,070
-
kW-mo/yr
|
$4,002
-
Tgal
|
$6,046 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs