| Assessment Year | 2006 |
|---|---|
| Principal Product | Industrial Adhesives |
| NAICS | 325520: Adhesive Manufacturing |
| SIC | 2891: Adhesives and Sealants |
| Sales Range | $100 M to 500M |
| # of Employees | 82 |
| Plant Area |
75,000
ft2
|
| Annual Production | 235,000,000
lb
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,855 | 1,633,560 |
kWh
|
$0.056 |
| Electricity Demand | $23,268 | 2,800 |
kW-mo/yr
|
$8.31 |
| Electricity Fees | $14,961 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $55,540 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,063 | $40,180 |
$13,673
245,606
kWh
|
$3,390
-
kW-mo/yr
|
|
| 02 | 2.4239: Eliminate or reduce compressed air usage | $3,719 | $2,400 |
$2,979
53,520
kWh
|
$740
-
kW-mo/yr
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,540 | $28 |
$1,208
21,703
kWh
|
$332
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $950 | $1,018 |
$792
14,225
kWh
|
$158
-
kW-mo/yr
|
|
| 05 | 2.1321: Replace fossil fuel equipment with electrical equipment | $32,268 | $31,176 |
$32,268
579,627
kWh
|
- | |
| TOTAL RECOMMENDED | $55,540 | $74,802 |
$50,920
914,681
kWh
|
$4,620
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs