Assessment Year | 2025 |
---|---|
Principal Product | NA |
NAICS | 611310: Colleges, Universities, and Professional Schools |
SIC | 8221: Colleges, Universities, and Professional Schools |
Sales Range | less than $500 k |
# of Employees | 100 |
Plant Area |
76,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 6,188
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $27,337 | 759,371 |
kWh
|
$0.036 | |
Electricity Demand | $74,759 | 4,820 |
kW-mo/yr
|
$15.51 | |
Natural Gas | $128,353 | 26,574 |
MMBtu
|
$4.83 | |
Waste Disposal Costs | |||||
Water Usage | $24,021 | 28,399 |
Tgal
|
$0.85 | |
TOTAL YEARLY COSTS | $254,470 | ||||
RECOMMENDED SAVINGS* | $20,252 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7311: Ventilation system to shut off when room is not in use | $10,697 | $45,926 |
$5,245
147,161
kWh
|
$5,452
-
kW-mo/yr
|
- | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $2,450 | $9,720 | - | - |
$2,450
-
MMBtu
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $1,938 | $15,980 |
$1,661
46,653
kWh
|
$277
-
kW-mo/yr
|
- | - | |
04 | 2.3141: Use battery storage for demand control | $1,620 | $14,000 | - |
$1,620
-
kW-mo/yr
|
- | - | |
05 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $1,338 | $5,515 |
$33
929
kWh
|
$141
-
kW-mo/yr
|
- | $1,164 | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,000 | $5,450 |
$627
17,540
kWh
|
$372
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $546 | $1,620 |
$339
9,470
kWh
|
$207
-
kW-mo/yr
|
- | - | |
08 | 2.2437: Recover waste heat from equipment | $545 | $572 |
$126
3,555
kWh
|
$419
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $119 | $551 |
$19
527
kWh
|
$101
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $20,252 | $99,334 |
$8,050
225,835
kWh
|
$8,588
-
kW-mo/yr
|
$2,450
-
MMBtu
|
$1,164 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs