Assessment Year | 2024 |
---|---|
Principal Product | Lower Limb Prosthetics |
NAICS | 339113: Surgical Appliance and Supplies Manufacturing |
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $50 M to 100M |
# of Employees | 70 |
Plant Area |
26,000
ft2
|
Annual Production | 70,000
units
|
Production Hrs. Annual | 2,085
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,515 | 1,435,118 |
kWh
|
$0.036 |
Electricity Demand | $70,490 | 5,754 |
kW-mo/yr
|
$12.25 |
TOTAL YEARLY COSTS | $122,005 | |||
RECOMMENDED SAVINGS* | $46,878 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $27,825 | $247,680 |
$12,667
351,860
kWh
|
$15,158
-
kW-mo/yr
|
- | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $10,585 | $5,800 | - |
$10,585
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $4,696 | $8,277 |
$1,387
38,544
kWh
|
$809
-
kW-mo/yr
|
$2,500 | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,557 | $6,277 |
$896
24,879
kWh
|
$1,661
-
kW-mo/yr
|
- | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $726 | $3,000 |
$726
20,176
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $489 | $1,818 |
$165
4,587
kWh
|
$324
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $46,878 | $272,852 |
$15,841
440,046
kWh
|
$28,537
-
kW-mo/yr
|
$2,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs