ITAC Assessment: UU0243
ITAC logo
ITAC Assessment: UU0243
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product NA
NAICS 721110: Hotels (except Casino Hotels) and Motels
SIC 7011: Hotels and Motels
Sales Range less than $500
k
# of Employees 300
Plant Area 365,000
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $223,662 6,766,550
kWh
Electricity Demand $219,279 11,342
kW-mo/yr
Natural Gas $470,461 52,866
MMBtu
TOTAL YEARLY COSTS $913,401
RECOMMENDED SAVINGS* $63,895 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,220

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7229: Air condition only space necessary $26,330 $19,500 $4,700
142,430
kWh
- - $21,630
-
MMBtu
02 2.3137: Use power during off-peak periods $15,800 $13,000 - - $15,800 -
03 2.2514: Cover open tanks $9,190 $7,340 - - - $9,190
-
MMBtu
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,631 $22,338 $2,574
77,997
kWh
$2,057
-
kW-mo/yr
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,244 $14,145 $1,686
51,077
kWh
$1,558
-
kW-mo/yr
- -
06 2.2614: Use cooling tower or economizer to replace chiller cooling $2,800 $6,300 $2,800
84,950
kWh
- - -
07 2.3212: Optimize plant power factor $1,900 $6,000 - - $1,900 -
TOTAL RECOMMENDED $63,895 $88,623 $11,760
356,454
kWh
$3,615
-
kW-mo/yr
$17,700 $30,820
-
MMBtu
TOTAL IMPLEMENTED $40,220 $39,140 $7,500
227,380
kWh
- $1,900 $30,820
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs