| Assessment Year | 2024 |
|---|---|
| Principal Product | NA |
| NAICS | 721110: Hotels (except Casino Hotels) and Motels |
| SIC | 7011: Hotels and Motels |
| Sales Range | less than $500 k |
| # of Employees | 300 |
| Plant Area |
365,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $223,662 | 6,766,550 |
kWh
|
$0.033 |
| Electricity Demand | $219,279 | 11,342 |
kW-mo/yr
|
$19.33 |
| Natural Gas | $470,461 | 52,866 |
MMBtu
|
$8.90 |
| TOTAL YEARLY COSTS | $913,401 | |||
| RECOMMENDED SAVINGS* | $63,895 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,220 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7229: Air condition only space necessary | $26,330 | $19,500 |
$4,700
142,430
kWh
|
- | - |
$21,630
-
MMBtu
|
|
| 02 | 2.3137: Use power during off-peak periods | $15,800 | $13,000 | - | - | $15,800 | - | |
| 03 | 2.2514: Cover open tanks | $9,190 | $7,340 | - | - | - |
$9,190
-
MMBtu
|
|
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,631 | $22,338 |
$2,574
77,997
kWh
|
$2,057
-
kW-mo/yr
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,244 | $14,145 |
$1,686
51,077
kWh
|
$1,558
-
kW-mo/yr
|
- | - | |
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,800 | $6,300 |
$2,800
84,950
kWh
|
- | - | - | |
| 07 | 2.3212: Optimize plant power factor | $1,900 | $6,000 | - | - | $1,900 | - | |
| TOTAL RECOMMENDED | $63,895 | $88,623 |
$11,760
356,454
kWh
|
$3,615
-
kW-mo/yr
|
$17,700 |
$30,820
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $40,220 | $39,140 |
$7,500
227,380
kWh
|
- | $1,900 |
$30,820
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs