Assessment Year | 2024 |
---|---|
Principal Product | NA |
NAICS | 621111: Offices of Physicians (except Mental Health Specialists) |
SIC | 8011: Offices and Clinics of Doctors of Medicine |
Sales Range | less than $500 k |
# of Employees | 200 |
Plant Area |
130,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 3,640
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $96,904 | 2,695,040 |
kWh
|
$0.036 |
Electricity Demand | $97,834 | 6,010 |
kW-mo/yr
|
$16.28 |
Electricity Fees | $16,932 | - |
|
- |
Natural Gas | $275,158 | 13,296 |
MMBtu
|
$20.69 |
TOTAL YEARLY COSTS | $486,828 | |||
RECOMMENDED SAVINGS* | $14,455 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,408 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2612: Use cooling tower water instead of refrigeration | $10,047 | $10,320 |
$4,365
121,249
kWh
|
$5,682
-
kW-mo/yr
|
- | |
02 | 2.2121: Increase amount of condensate returned | $1,601 | $7,755 | - | - |
$1,601
-
MMBtu
|
|
03 | 2.6218: Turn off equipment when not in use | $1,286 | $1,500 |
$1,286
35,728
kWh
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $977 | $113 |
$977
27,147
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $544 | $1,387 |
$231
6,414
kWh
|
$313
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $14,455 | $21,075 |
$6,859
190,538
kWh
|
$5,995
-
kW-mo/yr
|
$1,601
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,408 | $10,755 |
$2,494
69,289
kWh
|
$313
-
kW-mo/yr
|
$1,601
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs