Assessment Year | 2023 |
---|---|
Principal Product | NA |
NAICS | 611110: Elementary and Secondary Schools |
SIC | 8211: Elementary and Secondary Schools |
Sales Range | less than $500 k |
# of Employees | 40 |
Plant Area |
48,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $12,805 | 353,440 |
kWh
|
$0.036 |
Electricity Demand | $27,313 | 1,664 |
kW-mo/yr
|
$16.41 |
Electricity Fees | $6,018 | - |
|
- |
Natural Gas | $21,020 | 1,942 |
MMBtu
|
$10.82 |
TOTAL YEARLY COSTS | $67,156 | |||
RECOMMENDED SAVINGS* | $9,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,783 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,358 | $31,190 |
$1,774
49,427
kWh
|
$3,584
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $2,200 | $255 |
$1,024
28,275
kWh
|
- |
$1,176
-
MMBtu
|
|
03 | 2.6218: Turn off equipment when not in use | $1,572 | $850 | - | - |
$1,572
-
MMBtu
|
|
04 | 2.7272: Install heat pipes / raise cooling setpoint | $425 | $255 |
$300
8,285
kWh
|
$125
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $9,555 | $32,550 |
$3,098
85,987
kWh
|
$3,709
-
kW-mo/yr
|
$2,748
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,783 | $31,445 |
$2,074
57,712
kWh
|
$3,709
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs