ITAC Assessment: UU0233
ITAC logo
ITAC Assessment: UU0233
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product NA
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range less than $500
k
# of Employees 40
Plant Area 48,000
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,805 353,440
kWh
Electricity Demand $27,313 1,664
kW-mo/yr
Electricity Fees $6,018 -
Natural Gas $21,020 1,942
MMBtu
TOTAL YEARLY COSTS $67,156
RECOMMENDED SAVINGS* $9,555 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,783

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,358 $31,190 $1,774
49,427
kWh
$3,584
-
kW-mo/yr
-
02 2.2437: Recover waste heat from equipment $2,200 $255 $1,024
28,275
kWh
- $1,176
-
MMBtu
03 2.6218: Turn off equipment when not in use $1,572 $850 - - $1,572
-
MMBtu
04 2.7272: Install heat pipes / raise cooling setpoint $425 $255 $300
8,285
kWh
$125
-
kW-mo/yr
-
TOTAL RECOMMENDED $9,555 $32,550 $3,098
85,987
kWh
$3,709
-
kW-mo/yr
$2,748
-
MMBtu
TOTAL IMPLEMENTED $5,783 $31,445 $2,074
57,712
kWh
$3,709
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs