ITAC Assessment: UU0223
ITAC logo
ITAC Assessment: UU0223
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Ice cream
NAICS 311520: Ice Cream and Frozen Dessert Manufacturing
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $1
M
to 5
M
# of Employees 8
Plant Area 43,000
ft2
Annual Production 450,000
lb
Production Hrs. Annual 2,000
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $148,458 1,587,936
kWh
Other Energy $81,198 5,497
MMBtu
Waste Disposal Costs
Water Usage $10,171 2,729
Tgal
TOTAL YEARLY COSTS $239,827
RECOMMENDED SAVINGS* $200,364 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $200,364

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Water Usage Savings Increase in Production Savings
01 4.452: Eliminate shift $171,281 $5,500 - - - - $171,281
02 2.4322: Use or replace with energy efficient substitutes $16,735 $51,600 - - $16,735
-
MMBtu
- -
03 2.2622: Replace existing chiller with high efficiency model $8,766 $26,767 $1,056
10,436
kWh
- - $7,710
-
Tgal
-
04 2.2121: Increase amount of condensate returned $3,305 $11,743 - $2,577
-
MMBtu
- $728
-
Tgal
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $277 $142 $277
2,733
kWh
- - - -
TOTAL RECOMMENDED $200,364 $95,752 $1,333
13,169
kWh
$2,577
-
MMBtu
$16,735
-
MMBtu
$8,438
-
Tgal
$171,281
TOTAL IMPLEMENTED $200,364 $95,752 $1,333
13,169
kWh
$2,577
-
MMBtu
$16,735
-
MMBtu
$8,438
-
Tgal
$171,281
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs