ITAC Assessment: UU0219
ITAC logo
ITAC Assessment: UU0219
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Rubber
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 200
Plant Area 180,000
ft2
Annual Production 130
ton
Production Hrs. Annual 8,400
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $174,704 5,210,100
kWh
Electricity Demand $262,465 14,974
kW-mo/yr
Electricity Fees $54,172 -
Natural Gas $248,965 61,469
MMBtu
TOTAL YEARLY COSTS $740,307
RECOMMENDED SAVINGS* $265,930 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,112

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $242,311 $1,768,555 $167,706
4,932,540
kWh
$300,885
-
kW-mo/yr
$95,827
-
MMBtu
$(-322,107.0)
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $17,112 $13,345 $6,404
188,367
kWh
$10,708
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $2,350 $2,350 $2,350
69,100
kWh
- - -
04 2.4322: Use or replace with energy efficient substitutes $1,850 $18,236 $1,850
54,429
kWh
- - -
05 2.6218: Turn off equipment when not in use $1,272 $172 $1,272
37,400
kWh
- - -
06 2.4145: Install isolation transformer on adjustable frequency drive $1,035 $729 $1,035
30,448
kWh
- - -
TOTAL RECOMMENDED $265,930 $1,803,387 $180,617
5,312,284
kWh
$311,593
-
kW-mo/yr
$95,827
-
MMBtu
$(-322,107.0)
TOTAL IMPLEMENTED $17,112 $13,345 $6,404
188,367
kWh
$10,708
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs