Assessment Year | 2023 |
---|---|
Principal Product | Rubber |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
180,000
ft2
|
Annual Production | 130
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $174,704 | 5,210,100 |
kWh
|
$0.034 |
Electricity Demand | $262,465 | 14,974 |
kW-mo/yr
|
$17.53 |
Electricity Fees | $54,172 | - |
|
- |
Natural Gas | $248,965 | 61,469 |
MMBtu
|
$4.05 |
TOTAL YEARLY COSTS | $740,307 | |||
RECOMMENDED SAVINGS* | $265,930 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,112 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $242,311 | $1,768,555 |
$167,706
4,932,540
kWh
|
$300,885
-
kW-mo/yr
|
$95,827
-
MMBtu
|
$(-322,107.0) | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $17,112 | $13,345 |
$6,404
188,367
kWh
|
$10,708
-
kW-mo/yr
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $2,350 | $2,350 |
$2,350
69,100
kWh
|
- | - | - | |
04 | 2.4322: Use or replace with energy efficient substitutes | $1,850 | $18,236 |
$1,850
54,429
kWh
|
- | - | - | |
05 | 2.6218: Turn off equipment when not in use | $1,272 | $172 |
$1,272
37,400
kWh
|
- | - | - | |
06 | 2.4145: Install isolation transformer on adjustable frequency drive | $1,035 | $729 |
$1,035
30,448
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $265,930 | $1,803,387 |
$180,617
5,312,284
kWh
|
$311,593
-
kW-mo/yr
|
$95,827
-
MMBtu
|
$(-322,107.0) | ||
TOTAL IMPLEMENTED | $17,112 | $13,345 |
$6,404
188,367
kWh
|
$10,708
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs