| Assessment Year | 2023 |
|---|---|
| Principal Product | plastic stretch and shrink wrap |
| NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
| SIC | 3081: Unsupported Plastics Film and Sheet |
| Sales Range | $50 M to 100M |
| # of Employees | 105 |
| Plant Area |
120,000
ft2
|
| Annual Production | 21,500,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $475,256 | 16,900,800 |
kWh
|
$0.028 |
| Electricity Demand | $428,064 | 27,907 |
kW-mo/yr
|
$15.34 |
| Electricity Fees | $115,570 | - |
|
- |
| TOTAL YEARLY COSTS | $1,018,890 | |||
| RECOMMENDED SAVINGS* | $71,267 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,700 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $14,031 | $23,302 | - | - | $14,031 | |
| 02 | 2.7243: Improve air circulation with destratification fans / other methods | $4,069 | $17,638 |
$2,613
92,985
kWh
|
$1,456
-
kW-mo/yr
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $2,776 | $6,969 |
$1,027
36,551
kWh
|
$1,749
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,274 | $495 |
$851
30,269
kWh
|
$423
-
kW-mo/yr
|
- | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $701 | $1,150 |
$356
12,679
kWh
|
$345
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $550 | $1,558 |
$275
9,802
kWh
|
$275
-
kW-mo/yr
|
- | |
| 07 | 2.3112: Store heated/ cooled water for use during peak demand periods | $24,046 | $226,100 |
$2,550
-
kWh
|
$21,496
-
kW-mo/yr
|
- | |
| 08 | 2.2691: Shut off cooling if cold outside air will cool process | $23,820 | $214,625 |
$15,997
569,169
kWh
|
$7,823
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $71,267 | $491,837 |
$23,669
751,455
kWh
|
$33,567
-
kW-mo/yr
|
$14,031 | ||
| TOTAL IMPLEMENTED | $22,700 | $49,962 |
$4,766
169,607
kWh
|
$3,903
-
kW-mo/yr
|
$14,031 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs