ITAC Assessment: UU0200
ITAC logo
ITAC Assessment: UU0200
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Hot water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range less than $500
k
# of Employees 6
Plant Area 33,000
ft2
Annual Production 598,068
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,369 454,626
kWh
Natural Gas $1,146,377 278,551
MMBtu
TOTAL YEARLY COSTS $1,177,746
RECOMMENDED SAVINGS* $47,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,392

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $41,228 $52,800 - $41,228
-
MMBtu
02 3.1191: Change procedures / equipment / operating conditions $3,992 $10,000 $(-283,517.0)
10,815,000
kWh
$287,509
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,392 $5,232 $2,392
34,668
kWh
-
TOTAL RECOMMENDED $47,612 $68,032 $(-281,125.0)
10,849,668
kWh
$328,737
-
MMBtu
TOTAL IMPLEMENTED $2,392 $5,232 $2,392
34,668
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs