Assessment Year | 2022 |
---|---|
Principal Product | Hot water |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | less than $500 k |
# of Employees | 6 |
Plant Area |
33,000
ft2
|
Annual Production | 598,068
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,369 | 454,626 |
kWh
|
$0.069 |
Natural Gas | $1,146,377 | 278,551 |
MMBtu
|
$4.12 |
TOTAL YEARLY COSTS | $1,177,746 | |||
RECOMMENDED SAVINGS* | $47,612 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,392 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $41,228 | $52,800 | - |
$41,228
-
MMBtu
|
|
02 | 3.1191: Change procedures / equipment / operating conditions | $3,992 | $10,000 |
$(-283,517.0)
10,815,000
kWh
|
$287,509
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,392 | $5,232 |
$2,392
34,668
kWh
|
- | |
TOTAL RECOMMENDED | $47,612 | $68,032 |
$(-281,125.0)
10,849,668
kWh
|
$328,737
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,392 | $5,232 |
$2,392
34,668
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs