| Assessment Year | 2022 |
|---|---|
| Principal Product | Water Distribution |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $1 M to 5M |
| # of Employees | 11 |
| Plant Area |
11,500
ft2
|
| Annual Production | 710,360
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $124,360 | 1,977,372 |
kWh
|
$0.063 |
| Electricity Demand | $72,382 | 9,282 |
kW-mo/yr
|
$7.80 |
| Electricity Fees | $16,274 | - |
|
- |
| Natural Gas | $1,288 | 120 |
MMBtu
|
$10.77 |
| TOTAL YEARLY COSTS | $214,304 | |||
| RECOMMENDED SAVINGS* | $50,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $48,391 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3137: Use power during off-peak periods | $13,098 | $10,000 | - | - | - | $13,098 | |
| 02 | 4.811: Demolish old building to reduce tax and insurance bills | $12,033 | $300 | - | - | - | $12,033 | |
| 03 | 2.8114: Change rate schedules or other changes in utility service | $10,900 | $3,000 | - | - | - | $10,900 | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $12,230 | $4,000 |
$1,330
18,083
kWh
|
- | - | $10,900 | |
| 05 | 2.3212: Optimize plant power factor | $1,591 | $6,000 | - | $1,591 | - | - | |
| 06 | 4.811: Demolish old building to reduce tax and insurance bills | $130 | $25 | - | - | - | $130 | |
| 07 | 2.2211: Use optimum temperature | $380 | $200 | - | - |
$380
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $50,362 | $23,525 |
$1,330
18,083
kWh
|
$1,591 |
$380
-
MMBtu
|
$47,061 | ||
| TOTAL IMPLEMENTED | $48,391 | $17,325 |
$1,330
18,083
kWh
|
- | - | $47,061 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs