ITAC Assessment: UU0193
ITAC logo
ITAC Assessment: UU0193
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Copper
NAICS 212234: Copper Ore and Nickel Ore Mining
SIC 1021: Copper Ores
Sales Range $100
M
to 500
M
# of Employees 600
Plant Area 236,790
ft2
Annual Production 53,700
units
Production Hrs. Annual 8,760
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,370,860 293,659,778
kWh
Electricity Demand $9,245,579 444,712
kW-mo/yr
TOTAL YEARLY COSTS $16,616,439
RECOMMENDED SAVINGS* $649,479 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $648,533

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.9114: Use solar heat to make electricty $269,225 $7,636,800 $251,907
10,036,140
kWh
$17,318
-
kW-mo/yr
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $371,933 $40,000 - $371,933
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,764 $4,720 $1,292
51,522
kWh
$1,472
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,736 $1,307 $1,282
51,070
kWh
$1,454
-
kW-mo/yr
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,875 $5,000 $879
35,000
kWh
$996
-
kW-mo/yr
06 2.7135: Install occupancy sensors $946 $3,500 $946
38,410
kWh
-
TOTAL RECOMMENDED $649,479 $7,691,327 $256,306
10,212,142
kWh
$393,173
-
kW-mo/yr
TOTAL IMPLEMENTED $648,533 $7,687,827 $255,360
10,173,732
kWh
$393,173
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs