| Assessment Year | 2021 |
|---|---|
| Principal Product | Refined Metal Ingots |
| NAICS | 331410: Nonferrous Metal (except Aluminum) Smelting and Refining |
| SIC | 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum |
| Sales Range | $100 M to 500M |
| # of Employees | 120 |
| Plant Area |
66,700
ft2
|
| Annual Production | 550
ton
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $482,402 | 12,835,200 |
kWh
|
$0.038 | |
| Electricity Demand | $515,115 | 28,428 |
kW-mo/yr
|
$18.12 | |
| Electricity Fees | $46,318 | - |
|
- | |
| Natural Gas | $163,550 | 37,340 |
MMBtu
|
$4.38 | |
| Waste Disposal Costs | |||||
| Water Usage | $46,560 | 8,000 |
Tgal
|
$5.82 | |
| Solid Waste (haz) | $10,000 | 37,787 |
lb
|
$0.26 | |
| TOTAL YEARLY COSTS | $1,263,945 | ||||
| RECOMMENDED SAVINGS* | $173,012 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $72,940 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $57,706 | $128,174 |
$34,179
909,510
kWh
|
$23,527
-
kW-mo/yr
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $36,240 | $6,760 | - |
$36,240
-
kW-mo/yr
|
- | - | |
| 03 | 2.7231: Use radiant heater for spot heating | $32,792 | $101,000 | - | - | - |
$32,792
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,515 | $5,046 |
$7,413
197,114
kWh
|
$5,102
-
kW-mo/yr
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $10,455 | $14,250 | - | - | $10,455 | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,132 | $22,614 |
$8,132
216,389
kWh
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,105 | $11,650 |
$4,799
127,712
kWh
|
$3,305
-
kW-mo/yr
|
- | - | |
| 08 | 2.7314: Reduce ventilation air | $4,129 | $4,000 |
$330
8,780
kWh
|
- | - |
$3,799
-
MMBtu
|
|
| 09 | 2.7221: Lower temperature during the winter season and vice-versa | $1,497 | $100 |
$113
3,000
kWh
|
- | - |
$1,384
-
MMBtu
|
|
| 10 | 2.7135: Install occupancy sensors | $1,441 | $1,625 |
$1,441
38,342
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $173,012 | $295,219 |
$56,407
1,500,847
kWh
|
$68,175
-
kW-mo/yr
|
$10,455 |
$37,975
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $72,940 | $41,806 |
$12,655
336,606
kWh
|
$44,648
-
kW-mo/yr
|
$10,455 |
$5,183
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs