Assessment Year | 2020 |
---|---|
Principal Product | Flexible packaging and labels |
NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
40,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 6,032
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $64,339 | 1,306,550 |
kWh
|
$0.049 | |
Electricity Demand | $63,581 | 3,680 |
kW-mo/yr
|
$17.28 | |
Electricity Fees | $20,051 | - |
|
- | |
Natural Gas | $29,821 | 4,774 |
MMBtu
|
$6.25 | |
Waste Disposal Costs | |||||
Solid Waste (non-haz) | $21,173 | 624,000 |
lb
|
$0.034 | |
TOTAL YEARLY COSTS | $198,966 | ||||
RECOMMENDED SAVINGS* | $34,784 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $19,782 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,439 | $15,243 |
$6,439
131,400
kWh
|
- | - | - | - | |
02 | 3.6192: Use a less expensive method of waste removal | $5,200 | $5,000 | - | - | - | - |
$5,200
-
lb
|
|
03 | 2.3212: Optimize plant power factor | $4,999 | $3,792 | - | - | $4,999 | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,803 | $4,803 |
$4,803
98,020
kWh
|
- | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,814 | $7,952 |
$2,572
52,492
kWh
|
$1,242
-
kW-mo/yr
|
- | - | - | |
06 | 2.2622: Replace existing chiller with high efficiency model | $3,039 | $17,334 |
$1,278
26,081
kWh
|
$1,761
-
kW-mo/yr
|
- | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,543 | $100 |
$1,715
34,995
kWh
|
$828
-
kW-mo/yr
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,268 | $212 |
$1,853
37,815
kWh
|
$415
-
kW-mo/yr
|
- | - | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,679 | $1,200 | - | - | - |
$1,679
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $34,784 | $55,636 |
$18,660
380,803
kWh
|
$4,247
-
kW-mo/yr
|
$4,999 |
$1,679
-
MMBtu
|
$5,200
-
lb
|
||
TOTAL IMPLEMENTED | $19,782 | $42,041 |
$13,857
282,783
kWh
|
$4,247
-
kW-mo/yr
|
- |
$1,679
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs