| Assessment Year | 2020 |
|---|---|
| Principal Product | Water |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $5 M to 10M |
| # of Employees | 10 |
| Plant Area |
2,500
ft2
|
| Annual Production | 7,500
Tgal
|
| Production Hrs. Annual | 2,921
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,055 | 1,858,800 |
kWh
|
$0.051 |
| Electricity Demand | $55,580 | 6,108 |
kW-mo/yr
|
$9.10 |
| Electricity Fees | $3,600 | - |
|
- |
| TOTAL YEARLY COSTS | $153,235 | |||
| RECOMMENDED SAVINGS* | $16,349 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,128 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,906 | - | - |
$5,906
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,729 | $15,550 |
$2,235
44,190
kWh
|
$1,494
-
kW-mo/yr
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,221 | $8,000 | - |
$3,221
-
kW-mo/yr
|
|
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $3,063 | - |
$2,346
46,371
kWh
|
$717
-
kW-mo/yr
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $251 | - |
$186
3,674
kWh
|
$65
-
kW-mo/yr
|
|
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $178 | - |
$134
2,651
kWh
|
$44
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $16,349 | $23,550 |
$4,901
96,886
kWh
|
$11,448
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $13,128 | $15,550 |
$4,901
96,886
kWh
|
$8,227
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs