| Assessment Year | 2004 |
|---|---|
| Principal Product | Knit hosiery and active wear |
| NAICS | 315110: Hosiery and Sock Mills |
| SIC | 2252: Hosiery, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 92 |
| Plant Area |
100,000
ft2
|
| Annual Production | 18,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,204 | 2,006,550 |
kWh
|
$0.047 |
| Electricity Demand | $41,857 | 7,372 |
kW-mo/yr
|
$5.68 |
| Electricity Fees | $5,414 | - |
|
- |
| Natural Gas | $93,905 | 10,098 |
MMBtu
|
$9.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,937 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,732 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.113: Install refrigeration system to cool product | $9,750 | - |
$(-1,632.0)
(-28,740)
kWh
|
- | - | - | - | $(-468.0) | - | $11,850 | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $8,603 | $1,000 | - |
$8,603
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 03 | 2.1133: Adjust burners for efficient operation | $1,163 | $800 | - | - |
$1,163
-
MMBtu
|
- | - | - | - | - | |
| 04 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $1,175 | $1,200 | - | - | - |
$375
-
Tgal
|
- | $500 | $300 | - | |
| 05 | 2.1333: Convert combustion equipment to burn oil | $21,805 | $15,800 | - | - |
$21,805
-
MMBtu
|
- | - | - | - | - | |
| 06 | 2.2121: Increase amount of condensate returned | $1,388 | $900 | - | - |
$1,388
-
MMBtu
|
- | - | - | - | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $1,037 | $1,335 | - | - |
$1,037
-
MMBtu
|
- | - | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $797 | $1,315 |
$492
16,221
kWh
|
$305
-
kW-mo/yr
|
- | - | - | - | - | - | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $219 | $100 |
$357
11,778
kWh
|
$222
-
kW-mo/yr
|
- | - | $(-160.0) | - | $(-200.0) | - | |
| TOTAL RECOMMENDED | $45,937 | $22,450 |
$(-783.0)
(-741)
kWh
|
$9,130
-
kW-mo/yr
|
$25,393
-
MMBtu
|
$375
-
Tgal
|
$(-160.0) | $32 | $100 | $11,850 | ||
| TOTAL IMPLEMENTED | $14,732 | $4,335 |
$(-1,275.0)
(-16,962)
kWh
|
$222
-
kW-mo/yr
|
$3,588
-
MMBtu
|
$375
-
Tgal
|
$(-160.0) | $32 | $100 | $11,850 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs