| Assessment Year | 2020 |
|---|---|
| Principal Product | Dialyzers, Saline Bags |
| NAICS | 339112: Surgical and Medical Instrument Manufacturing |
| SIC | 3841: Surgical and Medical Instruments and Apparatus |
| Sales Range | greater than $500 M |
| # of Employees | 1,800 |
| Plant Area |
120,000
ft2
|
| Annual Production | 100,000,000
units
|
| Production Hrs. Annual | 8,700
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $990,000 | 14,154,551 |
kWh
|
$0.070 | |
| Natural Gas | $717,178 | 204,908 |
MMBtu
|
$3.50 | |
| Waste Disposal Costs | |||||
| Water Usage | $585,000 | 117,000 |
Tgal
|
$5.00 | |
| TOTAL YEARLY COSTS | $2,292,178 | ||||
| RECOMMENDED SAVINGS* | $600,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $115,777 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $471,950 | $2,795,000 |
$777,000
11,100,000
kWh
|
$(-186,550.0)
-
MMBtu
|
- | $(-118,500.0) | |
| 02 | 3.4113: Treat and reuse rinse waters | $72,249 | $60,000 |
$(-6,251.0)
(-89,300)
kWh
|
- |
$78,500
-
Tgal
|
- | |
| 03 | 3.4146: Change method of deionized water production | $35,350 | $180,000 |
$27,650
395,000
kWh
|
$7,700
-
MMBtu
|
- | - | |
| 04 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $12,331 | $22,500 | - |
$12,331
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,178 | $17,274 |
$8,178
116,834
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $600,058 | $3,074,774 |
$806,577
11,522,534
kWh
|
$(-166,519.5)
-
MMBtu
|
$78,500
-
Tgal
|
$(-118,500.0) | ||
| TOTAL IMPLEMENTED | $115,777 | $257,274 |
$29,577
422,534
kWh
|
$7,700
-
MMBtu
|
$78,500
-
Tgal
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs