Assessment Year | 2020 |
---|---|
Principal Product | Dialyzers, Saline Bags |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | greater than $500 M |
# of Employees | 1,800 |
Plant Area |
120,000
ft2
|
Annual Production | 100,000,000
units
|
Production Hrs. Annual | 8,700
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $990,000 | 14,154,551 |
kWh
|
$0.070 | |
Natural Gas | $717,178 | 204,908 |
MMBtu
|
$3.50 | |
Waste Disposal Costs | |||||
Water Usage | $585,000 | 117,000 |
Tgal
|
$5.00 | |
TOTAL YEARLY COSTS | $2,292,178 | ||||
RECOMMENDED SAVINGS* | $600,058 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $115,777 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $471,950 | $2,795,000 |
$777,000
11,100,000
kWh
|
$(-186,550.0)
-
MMBtu
|
- | $(-118,500.0) | |
02 | 3.4113: Treat and reuse rinse waters | $72,249 | $60,000 |
$(-6,251.0)
(-89,300)
kWh
|
- |
$78,500
-
Tgal
|
- | |
03 | 3.4146: Change method of deionized water production | $35,350 | $180,000 |
$27,650
395,000
kWh
|
$7,700
-
MMBtu
|
- | - | |
04 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $12,331 | $22,500 | - |
$12,331
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,178 | $17,274 |
$8,178
116,834
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $600,058 | $3,074,774 |
$806,577
11,522,534
kWh
|
$(-166,519.5)
-
MMBtu
|
$78,500
-
Tgal
|
$(-118,500.0) | ||
TOTAL IMPLEMENTED | $115,777 | $257,274 |
$29,577
422,534
kWh
|
$7,700
-
MMBtu
|
$78,500
-
Tgal
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs