Assessment Year | 2019 |
---|---|
Principal Product | Composite Parts |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
101,500
ft2
|
Annual Production | 3,140
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $91,553 | 2,503,839 |
kWh
|
$0.037 | |
Electricity Demand | $78,586 | 4,695 |
kW-mo/yr
|
$16.74 | |
Electricity Fees | $34,066 | - |
|
- | |
Natural Gas | $29,330 | 3,651 |
MMBtu
|
$8.03 | |
Waste Disposal Costs | |||||
Water Usage | $10,569 | 1,467 |
Tgal
|
$7.20 | |
TOTAL YEARLY COSTS | $244,104 | ||||
RECOMMENDED SAVINGS* | $23,670 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $10,461 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $10,657 | $600 | - | - | $10,657 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,981 | $14,585 |
$4,024
109,639
kWh
|
$2,957
-
kW-mo/yr
|
- | |
03 | 2.3212: Optimize plant power factor | $1,742 | $2,500 | - | - | $1,742 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,661 | - |
$1,022
27,857
kWh
|
$638
-
kW-mo/yr
|
- | |
05 | 2.7135: Install occupancy sensors | $1,532 | - |
$1,532
41,750
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $810 | $129 |
$498
13,578
kWh
|
$311
-
kW-mo/yr
|
- | |
07 | 2.7221: Lower temperature during the winter season and vice-versa | $288 | $100 |
$213
5,742
kWh
|
$75
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $23,670 | $17,914 |
$7,290
198,566
kWh
|
$3,981
-
kW-mo/yr
|
$12,399 | ||
TOTAL IMPLEMENTED | $10,461 | $14,685 |
$6,791
184,988
kWh
|
$3,670
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs